CPS Low-Flow Showerheads and Aerators
Header image: illustration of the type of work described, not a photo of a CG Service Pros project.
Yes, both are covered. Water-saving showerheads and faucet aerators are on the CPS Energy Multifamily Program's measure list for qualifying properties. The program's Measures Overview limits them to electric heating and sets flow limits for the old and new devices. As a participating trade ally, CG installs them unit by unit, often during the same visit as other in-unit work.
They are the smallest items on the list. They are also among the fastest to install, and on the right property they help a project reach the program's minimum. Here is what qualifies, how our unit visits go, and how we help keep resident complaints down. If you want a count for your property, request a site walk.
What qualifies
The CPS Measures Overview lists these conditions for the two water-saving devices:
| Device | Existing device | New device | Condition |
|---|---|---|---|
| Low-flow showerhead | 2.5 gallons per minute (GPM) or more | 2.0 GPM or less | Electric heating only |
| Low-flow faucet aerator | 2.2 GPM or more | 1.5 GPM or less | Electric heating only |
Two things follow from that table.
First, the existing fixture has to be a higher-flow device. A unit that already has a low-flow showerhead from a past turn will not qualify for a replacement.
Second, the electric heating condition matters. CG confirms how it applies at your property during the site walk, especially if water heaters are gas-fired or the property has a mix of fuels. We settle that before the devices go into the scope.
The overview has no printed effective date, and CPS says program offerings can change without notice. CG confirms current requirements for your project before the scope is written.
Why small measures matter on a CPS project
The Measures Overview sets a minimum: a property must qualify for attic insulation or for at least two other measures. Showerheads and aerators sit on that list of other measures with Wi-Fi thermostats, A/C tune-ups, solar screens and air sealing.
That matters most for properties where attic insulation is not a fit, such as buildings with recently insulated attics. Showerheads and aerators are grouped together as water-saving devices on the overview, so CG confirms whether they count as one measure or two on your project.
They also ride along well. Crews are already inside each unit for thermostats or tune-ups, so swapping a showerhead and two aerators adds little time to a visit the resident is already expecting. And every gallon of hot water a property does not use is water its heaters do not have to heat.
Who installs them and how a unit visit runs
All program work is done by an approved, registered trade ally. CG works in the program as a participating trade ally, so our crews handle the install from scoping to the final unit list.
A typical CG in-unit visit for water devices looks like this:
- Notice goes out to residents before the work day, with the date, time window and what will be replaced.
- The crew checks the existing devices. Flow rate is confirmed or read from the fixture, so only qualifying devices are swapped.
- The new devices go in, with fresh thread tape where needed.
- The crew runs water and checks for leaks at the shower arm and each faucet.
- The unit is recorded, with what was installed and what was skipped and why.
- A door hanger or note tells the resident what changed and who to call with questions.
Scheduling usually runs building by building, with maintenance staff or a leasing team member handling keys and access. Units with pets, medical needs or "do not enter" requests get flagged before the crew arrives.
From the field: "Walk a few units per floor plan before the scope is written. Some units already have low-flow heads from past turns, and some have handheld showers or specialty fixtures that need a different device. A quick sample gives an honest count for the LOI."
CG's field team
How residents react, and how to keep complaints down
Most residents never notice the change. The ones who do usually ask the same questions:
- "Is my water pressure lower?" Pressure in the line does not change. Flow through the head is lower, and a good low-flow showerhead is designed to feel strong at that flow.
- "Why does the kitchen sink take longer to fill a pot?" An aerator limits flow at the faucet. For filling large pots, residents can expect a slightly longer wait.
- "Can I put my old showerhead back?" Ask residents to call the office instead. Swapping the old device back undoes the work, and the office can look at the specific problem.
From the field: "Most pushback comes from surprise, not from the showerhead. When the notice explains what is being replaced and why, and the office knows how to answer the pressure question, the calls drop off fast."
CG's field team
We suggest routing resident questions through the leasing office so one person gives the same answer every time, and we give the office the answers ahead of time. Keep operational issues, like a locked unit or a leak found during the install, on a separate line between the crew and maintenance.
What maintenance should know after the install
- Keep the unit list we hand over. It shows which units got new devices and which were skipped.
- Stay low-flow on turns. When a showerhead or aerator gets replaced later, use a device at or below the same flow rating.
- Clean aerators as part of routine checks. San Antonio water is hard, and mineral buildup in an aerator can make a faucet feel weak. Cleaning the screen usually fixes it.
- Report leaks early. A drip at a new showerhead is usually a thread-tape fix.
How payment works with CG
In San Antonio, CG Service Pros works only in the CPS Energy Multifamily Program, as a participating trade ally. CPS Energy pays the trade ally once all required documents, including the final invoice and W-9, are submitted, typically within 6 to 8 weeks. CG collects that payment directly from the program at the end of the job.
CPS says its incentives typically cover all or most of the cost of qualifying equipment. If any recommended work needs an owner contribution, the Letter of Intent shows that amount before you sign.
Frequently Asked Questions
Are low-flow showerheads and aerators part of the CPS Energy Multifamily Program?
Yes. Water-saving showerheads and faucet aerators are both listed measures in the CPS Energy Multifamily Program for qualifying San Antonio properties.
Which showerheads qualify for replacement?
Per the program's Measures Overview, the existing showerhead must flow at 2.5 GPM or more, and the new one must be 2.0 GPM or less. For aerators, the existing device must be 2.2 GPM or more, and the new one 1.5 GPM or less.
Do properties with gas water heaters qualify?
The Measures Overview lists both water devices as electric heating only. CG confirms how that applies to your property during the site walk, before they go into a scope.
Who installs the devices?
An approved, registered trade ally does all program work. CG is a participating trade ally and installs the devices unit by unit, usually during the same visit as other in-unit measures.
Will residents notice lower water pressure?
Line pressure stays the same. Flow through the fixture is lower. Most residents do not notice, and a clear notice ahead of the work answers most questions.
Do these devices count toward the two-measure minimum?
They are listed measures, so they can count toward the minimum of two measures when attic insulation is not part of the project. CG confirms during scoping whether showerheads and aerators count as one measure or two on your project.
Next step
CG Service Pros has handled rebate projects for more than five years and completed more than 4,500 multifamily units in a single year. If your San Antonio property may qualify, request a site walk or call us at (512) 843-7444. We walk your units with you, write the scope, do the installs, handle the program paperwork and collect the incentive directly. You can also read more about our San Antonio multifamily work.
Sources
Program details checked November 9, 2026: